Refine Sub-Cut for Parking Pad
At 7:00 in
Building a flagstone wall and prepping for pavers day1
What happens here
After the initial rough grading, set up string lines across the parking pad area to establish the precise depth and pitch. The parking pad will not be flat but will have a consistent angle from the existing driveway up to the new retaining wall. Use the mini excavator to perform the final 'sub-cut', carefully removing soil to achieve the exact desired depth relative to the string lines. This precision is critical because the depth of the sub-cut dictates the final height of the base material, sand, and pavers. Regular measurements from the string line are taken to ensure accuracy and prevent over-excavation. Be particularly careful in areas adjacent to existing structures or old retaining walls to avoid undermining them.
Goal: Precisely excavate the sub-base for the paver parking pad using a mini excavator and string lines to ensure the correct depth and desired pitch.
Tools and materials
- Mini Excavator
- Shovels
- String Line
- Tape Measure
What they say
(2,385 characters)Hide
What they say
(2,385 characters)Auto-generated from the video audio.