Install New Class 5 Base Material for Parking Pad

11:09
18:39
79.2K views

At 11:09 in

Building a flagstone wall and prepping for pavers day1

What happens here

Import new Class 5 limestone aggregate to fill the excavated parking pad area. This material, distinct from the recycled Class 5, consists of 3/4-inch rock with fines that compact firmly. Spread the Class 5 material using the skid steer and hand tools (shovels, rakes) to achieve an even layer at the correct elevation, guided by the string lines. Once spread, use a plate compactor to thoroughly compact the Class 5 material in multiple passes. This compaction is crucial for preventing settling and ensuring a stable, durable base for the pavers. The base is compacted even if it needs more material, to ensure a solid foundation against potential bad weather before the next layer is added.

Goal: Import and spread new Class 5 limestone aggregate over the prepared sub-base, rake it level, and compact it thoroughly to create a stable foundation for the pavers.

Tools and materials

  • Dump Trailer
  • Plate Compactor
  • Rakes
  • Skid Steer
  • String Line
  • Tape Measure
  • Class 5 Limestone Aggregate

What they say

Hide

foot rain is in the forecast and both Blaine and Tim need the exact same equipment on two different job sites so they put a plan together cuz I'm gonna need the dump trailer tomorrow to serve a project I could get maybe delay one more day you're gonna need it you know you'll use it in the morning cuz I'll need it right away I mean I'll need the mini X and the I didn't ever taken down you can have that I can start taking some trees down but it'd be nice to have a dump trailer but you're gonna need it a little bit longer yeah yeah you pick it up tonight so we ran the company for 20-plus years without ever owning a dump trailer and now that we have one they're finding it difficult to get by without it so you're gonna need it for another half a day he's not don't you yeah I mean they're also at the stage where they've got to address what they're going to do with that tricky retaining wall we know they can't dig it out with a piece of equipment and jeopardize undermining it so everything has to be done by hand okay I got that this all excavated down how they are definitely gonna need to do a thing over there after they've got the sub-base expose they immediately bring in new class-five and get that prepped and ready I think that's good go check alright class 5 using the class 5 for the base for the compaction you don't need the drainage like you would with the 3/4 clear behind the wall just cuz this finds we import new classified base even though it was an existing driveway there before simply because it gives us control we know exactly what material we're going to be installing our new paper driveway on and so this has to be levelled and compacted before it can be used before they hit it with a packer they're gonna put up their string line and make sure that they've got their elevations awesome so I mean the ArcLight that you're saying class 5 needs to be three inches three inches below so that's three inches below the string line yeah but they're finding out they're not quite there yet yeah and then an inch of sand and then the pavers and then packet yeah we're about six inches there it's about five and a half right there so they're still too deep and they don't have enough material to bring it up to the right grade that means they need to get more classified but before they do that they're going to pack and prep this to make sure that it's sealed just in case any bad weather comes before the next layer of classified can go down the papers show up ahead of…