The project starts with an overview of the challenging job site conditions, including limited space for machinery and city regulations preventing overnight equipment parking on the street. Despite these challenges, stone materials for a new retaining wall are brought in via a skid steer. An excavator is also brought onto the narrow site to begin the initial digging. The goal is to build a flagstone wall to retain soil for a planting area and transform the old driveway into a parking pad.
Goal: The crew begins by assessing the tight job site, which is a former driveway between two houses, and prepares for excavation. Stone materials for the wall are delivered, and heavy machinery is brought in.
Tools and materials
- Flagstones
- Mini Excavator
- Pallets
- Skid Steer Loader