What happens here

The construction of the retaining wall proceeds by stacking subsequent courses of interlocking blocks. After every few layers of blocks are laid, the area directly behind the wall is meticulously backfilled with generous amounts of crushed rock. This permeable backfill is then thoroughly compacted using the plate compactor. This continuous layering of blocks, geogrid, and compacted crushed rock creates a highly porous and stable zone. This system is critical for allowing water to drain freely, preventing the buildup of hydrostatic pressure against the building's foundation and the retaining wall, which was the original cause of the wall's failure.

Goal: The retaining wall is progressively built with layers of blocks, and the backfill zone is continuously filled with permeable crushed rock and compacted to prevent hydrostatic pressure.

Tools and materials

  • Concrete Adhesive (e.g
  • Milwaukee M12 Caulking Gun)
  • Crushed Rock
  • Geogrid
  • Plate Compactor
  • Shovels/Rakes

What they say

Hide

that's how you get that block to properly pin and when you line it all up it automatically sets it back now you've got a solid block and it's a mortarless system here's something i really want to cover with you guys this rock right here is the key and we always go heavy you're technically only supposed to need 12 inches of rock we like to put in a lot more rock it's cheap cheap insurance and this is what keeps these walls from experiencing hydrostatic blowout where the wall has too much water pressure can't go through and it's also the reason why we don't technically need drain tile we will put drain tile in because it makes customers happy because they smile and they see a drainage system but this rock makes the entire wall porous i've actually said if you ever see a drainage outlet on a retaining wall operating that wall's in a state of failure because the entire wall is supposed to just allow the water to just go through it it's a very porous system when it's all done properly together and you can see here how we over engineer this now this is actually soil we imported this is not the soil that we dug out we hauled that nasty stuff out this is fresh soil we brought in so the kitty cat right there she's wearing a winter i call them winter tracks uh it's an all season track but i call them winter tracks because it just dominates in wintertime and you guys we've got four epic snow plowing videos coming out i'm serious so excited so excited okay look at this block it drives me nuts i hate this block and i just don't like to see people use this see how sam's just throwing them in they're light this is why a lot of companies will choose this block and they'll use this block because they're so light it's easy to work with but they also don't make strong walls how do you connect these blocks together do you guys see a pin system there's no pin system in these blocks they have little tiny lips on the back of the block and that little limp is what is the only thing that holds them together and then you have to core fill the block but a lot of times guys don't core fill the block right they're cutting steps and that's why these walls tend to have problems when they really don't need to have problems hey real quick you guys not real quick i want to talk about like i still haven't got my element banner i don't know how long it's been but i still love the company i don't know if they want to be like a silent sponsor of the channel but they do sponsor and help me make…