Skip to main content

Construct Retaining Wall with Versa-Lok Blocks

3:09
24:25
113K views

At 3:09 in

We hit a Buried Line -on the Last job of the season.

What happens here

The retaining wall is built using Versa-Lok blocks, known for their solid construction and mortar-less installation. The blocks are dry-stacked, and their unique pinning system ensures each course locks into the one below, creating a stable, set-back structure. Geogrid is laid every two to four courses and extended into the backfill to integrate the wall with the surrounding soil, enhancing its resistance to lateral pressure. The goal is to create a 'porous system' that allows water to pass through, preventing hydrostatic pressure buildup against the foundation.

Goal: A new retaining wall is constructed around the window well using Versa-Lok blocks, which are solid and connect using a unique pinning system for stability without mortar. Geogrid is integrated every few courses to further reinforce the wall and improve soil stability, ensuring a robust and well-draining structure.

Tools and materials

  • Adhesive (Sikaflex Construction Sealant)
  • Caulking Gun (Milwaukee M12 FUEL)
  • Concrete Saw (Husqvarna)
  • Geogrid
  • Measuring Tape and Level
  • Pins
  • Plate Compactor
  • Shovels/Rakes
  • Versa-Lok Retaining Wall Blocks

What they say

Hide

the public utilities don't have to mark private lines they're not responsible for that this was a private unmarked line and so then we have to start to play sherlock holmes and figure out whose line it is now in this case we're going to put it back together and we track down that this is actually an irrigation line so then we called out the irrigation contractor responsible on the site to make sure that he was good with the way we repaired this now if this was a cable line or a private electrical line something that we're really not comfortable doing that's when we would call out a contractor to fix it so here's how i look at it if i've called in all my utility locates and they've clearly marked where all the lines are and i snagged that bugger that's on me to pay that bill but if a line is not marked and i hit that line then i've got some arguing rights and sometimes that happens where a line gets mismarked they've got to be within about three feet is the general rule that i've heard if they're more than three feet off from a line then the contractor may not be responsible for the repair of that line but if they've marked that line and they're within three feet of that line on either side of it and you hit that line that's on you you've got to be careful that's at least the way i understand it and these rules change is going to be different from different parts of the country today we got our dump truck driver on his way out his hand he's going to haul some junk on out of here for us make some more room and uh yes we're gonna need a lot of fill but now here's the flip side of the coin if we did not mark this job site and we anything we hit is now our responsibility if we didn't do a utility locate on this thing we failed to properly notify the companies we are 100 responsible for anything and everything we have that's why it's really important to follow those utility locate guidelines and to document the start of your project to make sure you know where all of the utilities are because where the responsibility lies can be one of those finger-pointing matches and this is i'm just sharing from experience what we've you know done over the past 25-30 years of digging in the dirt and finding goodies [Music] some people have said well you know why do you use this grapple for digging why do you use it for this you know it's one of those tools that it's maybe not perfect for digging but once you start to get familiar with it it's you're just like ah i don't…

Auto-generated from the video audio.