Demolish Old Timber Retaining Wall

1:04
16:47
61.4K views

At 1:04 in

Did we STOP losing money yet?!? 2/4

What happens here

The excavator begins to dismantle the old timber retaining wall. Sections of the timber are carefully extracted from the soil, sometimes requiring a reciprocating saw to cut embedded posts. This phased demolition strategy is employed to avoid hogging up the entire parking lot with debris and to allow for material reuse, as some removed soil will be used for backfill.

Goal: Remove sections of the existing timber wall efficiently and in phases.

Tools and materials

  • Daewoo Excavator
  • Dump Truck
  • Volvo Skid Steer

What they say

Hide

freeze fall state [Music] foreign so we're not tearing out the entire retaining wall from start to finish because we don't want to basically hog up the entire parking lot to do that so we're going to leave some of it in place while we build and then we're going to take out just enough that we can build it back up and then use that material to backfill the other portion of the retaining wall so it's kind of like we're flipping the soil from one side of the site to the other side of the site but when it gets really bad like this stuff we have to haul it out [Music] so we found out that that parking lot has flooding issues every single year that's

Auto-generated from the video audio.