Adjust Demolition for Geogrid and Drainage

2:47
16:47
61.4K views

At 2:47 in

Did we STOP losing money yet?!? 2/4

What happens here

Upon discovering that the parking lot frequently experiences flooding and water issues, the demolition plan is modified. Instead of leaving significant remnants of the old timber wall, more of it is removed to make space for the geogrid, which requires a 6-foot setback from the new block wall. The existing timber, though structurally sound, is removed to facilitate the necessary geogrid installation for enhanced stability and to create proper drainage behind the new wall.

Goal: Create sufficient space for geogrid installation and improve site drainage.

Tools and materials

  • Daewoo Excavator
  • Reciprocating Saw
  • Volvo Skid Steer

What they say

Hide

flooding issues every single year that's what we were told at least so all of these things started to come to light after we had completely wrapped up the entire retaining wall and a person came out that i think lived in the association and just started to share with us all of the issues they had they have um they have to drill holes in the parking lot because they get water blisters forming i've never heard of that is that crazy uh the units are flooding someone told us i mean it's just one thing after another on this site that would have been nice if we would have known about it before we got [Music] started [Music] we're running a little behind today because i uh we needed glue and i had to turn around and run back up to my house to get it because i haven't been keeping it in the truck and keep it in my house so it doesn't freeze and get wrecked because that stuff is expensive this is sam's favorite caulking gun i think he'll probably walk you through it but in the corners when we come to our corners you can't always get the pin holes to line up so we heavily glue the corners and we'll show you how we build a corner we actually overlay the corners and overcompensate them [Music] you'll see in the bank some of there's some of the dead men left in there sam is going to do a really good explanation of why that's okay to leave in place he does it as good as anybody i know can do it so we'll just let him talk about that in a little bit that other retaining wall that's above us that will get yanked and hauled out it's just some of those dead men can stay in place [Music] quite a pretty good day today again we got a lot a lot done god site's so muddy you can hear it squish so plan for tomorrow first thing the rest of this upper wall is coming out we need to be six feet back from the front of our blocks for the geo grid we're at like four right now so we got two more feet to go that's gotta come down [Applause] [Music] see if we tear it out too fast and then we get a rain or whatever it just gives us a little bit more control over the site to remove it in sections and build in sections and also conserves more of the site itself we don't tear everything out all at once but it is a little more difficult to work

Auto-generated from the video audio.