What happens here

The base course of the interlocking block wall is laid on a prepared, leveled gravel bed. Concrete adhesive is applied generously between blocks, especially at corners where pins might not align perfectly. Workers place the Versa-Lok standard units, ensuring they are level and properly seated with a rubber mallet. Geogrid is rolled out and secured behind the blocks, extending back into the slope, and gravel is backfilled over it in 2-foot lifts. Each lift of gravel and soil is compacted using a plate compactor and a heavy sheepsfoot packer to ensure stability and proper drainage, literally sealing the soil to prevent water wicking into the wall.

Goal: Build the foundational courses of the interlocking block retaining wall with proper adhesion, leveling, geogrid, and compaction.

Tools and materials

  • Caulk Gun (Milwaukee M18)
  • Concrete Adhesive
  • Geogrid
  • Level
  • Plate Compactor (Wacker)
  • Rakes
  • Rubber Mallet
  • Sheepsfoot Packer (10
  • 000 lb)
  • Shovels
  • Gravel
  • Soil/Dirt

What they say

Hide

work we use that grapple for everything we're just used to using it now i mean we can use it like a bucket we use it for demolition we use it for boulder wall installation i mean if we were gonna go dig a full basement or something like that we'd take it off but for just what we do it's just like having an actual hand you know compared to a tilt rotator or something else uh that rotates around like this they don't have a very good grapple or thumb on them like with this thing this is this is like having a big old mitt you're working with it's pretty nice and it rotates in all the same directions as a tilt rotator basically it has just has a different learning curve look at all the rock and the retaining wall so even though we're burying that rock we've at times we've got two feet of rock and then it kind of this is the face of the wall we put the rock in and let it fluff down and then we put the dirt up but we always keep that 12 inches exposed even though below it is almost two feet of rock and then it goes back down to 12 inches and then two feet that's how we build it in sections going up the more drainage aggregate you have the the less your your actual drain tile will work i started to explain this in the other video but here's a great example by over compensating on the drainage aggregate the entire wall now will weep there will be no water getting stuck in any one zone and therefore the drain tile should never actually function this is kind of a cool just top down that you see how we build these things all right so we modified our plant a little bit initially we were going to leave the remnants of this corner of the old timber wall in but we are going to get a little bit more grid in off of the corner in order for us to get it in at the length we want it to be this has to come out now normally it would be fine to to leave that in there there's a ton of dead men going back in there this wall was built extremely solid wasn't going to go anywhere so normally you can bury that stuff and to rot they need moisture air and sunlight and when you get timbers for example encapsulated in that hyper compacted soil where it's not getting access to any light or any oxygen they're not going to rot they'll get waterlogged like a son of a gun you dig run out they'll be weighing you know four times as much as they went in but they won't rot so it's normally all right to leave that kind of stuff in there and the only reason we're taking it out is so that we can get…

Auto-generated from the video audio.