During further excavation for the wall's base course, a significant amount of groundwater suddenly pours into the trench, filling it with approximately 4 inches of water. This unexpected water ingress requires immediate action and a change in plans. After consulting with the engineer, the solution involves excavating the base an additional 3 feet deep. To create a stable foundation in wet conditions, a 'pyramid' base is constructed, which involves layering drainage rock and geo-grid, wider at the bottom and tapering upwards. This design accommodates the lateral pressure of the blocks and provides robust drainage for the excessive water.
Goal: Significant groundwater is encountered during excavation, necessitating a deeper, wider base with extra drainage aggregate according to engineering specifications.
Tools and materials
- Daewoo 75V Excavator Daewoo
- Excavator Grapple Attachment
- Drainage Aggregate (Rock) Unspecified
- Geo-grid Fabric