Addressing Unexpected Water and Soil Correction

13:33
16:47
61.4K views

At 13:33 in

Did we STOP losing money yet?!? 2/4

What happens here

During further excavation for the wall's base course, a significant amount of groundwater suddenly pours into the trench, filling it with approximately 4 inches of water. This unexpected water ingress requires immediate action and a change in plans. After consulting with the engineer, the solution involves excavating the base an additional 3 feet deep. To create a stable foundation in wet conditions, a 'pyramid' base is constructed, which involves layering drainage rock and geo-grid, wider at the bottom and tapering upwards. This design accommodates the lateral pressure of the blocks and provides robust drainage for the excessive water.

Goal: Significant groundwater is encountered during excavation, necessitating a deeper, wider base with extra drainage aggregate according to engineering specifications.

Tools and materials

  • Daewoo 75V Excavator Daewoo
  • Excavator Grapple Attachment
  • Drainage Aggregate (Rock) Unspecified
  • Geo-grid Fabric

What they say

Hide

with the smaller packer all right uh you guys are gonna have to excuse my french on this but today just went here's what's going on so this is this is gonna be our outside 90 right here and then the wall is going to start swinging out that way the first scoop or second scoop we took with the excavator through here water to start pouring in that's four inches of water sitting there where our bases are supposed to be going which is like the last thing you want to see when you're trying to put in a base for a wall uh we're not 100 sure where it was coming in from it filled in so fast here's what we're going to do to alleviate these water problems we're having on our corner though so we heard back from the engineer and all he wants us to do is go down like three feet and just go extra heavy with the base so that the water has somewhere to go um and in order to do that obviously we have to excavate down three feet we just filled this in right now because there's a whole lot of kids running around this complex and tim didn't want any of them falling in there getting hurt but in order to get down that three feet there's a ratio so for every foot you go down you have to go a foot out so we have to cut a chunk pyramid of the parking lot out in order to get that room in front of where our wall is gonna be to do this correction so three feet down we need three feet in front uh we're gonna do that right away in the morning and then uh after that as long as nothing else goes wrong we are just gonna get in as much base as we can through here okay so it's not technically three feet

Auto-generated from the video audio.