Delivery and Initial Spreading of Soil

5:58
16:52
92.2K views

At 5:58 in

Dissed by The Building Inspector! #fail

What happens here

Several dump trucks deliver additional soil to the site, depositing it near the street. Workers immediately begin sweeping any spilled dirt from the street to adhere to regulations. The compact track loader then starts moving the newly delivered soil from the pile towards the pool, preparing it for distribution within the backfill area. This step emphasizes the importance of swift action to manage materials and maintain a clean work environment.

Goal: Receive delivered soil from dump trucks and immediately begin the process of moving and spreading it into the pool area, ensuring street cleanliness is maintained.

Tools and materials

  • Broom
  • Compact Track Loader (Skid Steer) CAT
  • Dump Truck
  • Shovel
  • Fill Soil

What they say

Hide

road like that but it was all metal oh crap we got no metal in here right just a little bit i swear that stuff i pulled off first was 10. yeah but this is a buster crab right here yeah it is right there yeah so yeah we we can i can call these guys and they'll take all the 10. that's all they do is 10. they're scrappers but i got their number if you get a load of scrap you don't have to put it on johnny but are you going to save that to the end most likely that's usually how we do it yeah we'll just save it to the end and then we'll throw it on the throw it on them guys or throw it on john one way or another that's not what i put in here's what i put in is nice and firm still soil i got you're gonna bridge just fine you're gonna bridge just fine that little bit of something we put a house on on a spot where the middle was like jello like legit jello and i called the engineer out i called a different engineer because i didn't like the first engineer's opinion because he's like no it's fine and i'm like that in my my opinion that can't be okay i call the second engineer out he came out and he's like yeah what's the problem like it's doing it's doing this but it was it was non-organic and the footings weren't on it and i learned i learned a pretty good lesson about bridging and soil composition and that's where i think you're going to be [Music] i question everything especially from engineers and architects and people that have very specific skill sets that i can then borrow that knowledge from on potential future projects the this house that we put over this questionable soils is still there today and still has zero issues and one of the things i learned was about something and pumping when you're in less than favorable conditions but still using optimum soils let me kind of break this down having a little bit of deflection in that soil as long as it's a non-organic material can sometimes with caution and understanding be an okay thing but you can mess that soil up if you over compact what happens is you'll get water down below and then if you're using a vibratory compactor and you're pounding the soil above it that water will actually wick up into your soil and disintegrate your results but if you use the right amount of compression compaction and you just gently squish that soil over the questionably questionable areas you can actually use the soil above it to create a bridging