Prepare the Foundation Trench
At 1:03 in
Chapter 1-the Start of a new wall
What happens here
The first critical step involves accurately marking the wall's layout to ensure proper alignment and dimensions. Following this, excavate a trench that is sufficiently wide and deep to accommodate the base course of blocks and the granular leveling pad. The trench must be excavated to a consistent depth along its entire length to establish a truly level base. After excavation, a layer of crushed gravel or road base material, typically 6-12 inches deep, is spread evenly within the trench. This granular material is then compacted using a plate compactor or hand tamper, and carefully leveled to create a precise, unyielding foundation for the first course of segmental retaining wall blocks. This initial leveling is paramount for the overall stability and appearance of the finished wall.
Goal: Begin by preparing the construction site, which includes marking out the retaining wall's path and excavating a level trench. This trench will serve as the crucial base for the entire wall structure. Once excavated, add and level a layer of crushed gravel or road base material within the trench to create a stable and well-draining foundation.
Tools and materials
- Long Level
- Mini Excavator (Bobcat 325)
- Plate Compactor
- Rakes
- Shovels
- Skid Steer (Caterpillar)
- String Line
- Tape Measure
- Crushed Gravel / Road Base Generic