What happens here

Once the first course of blocks is secured, the trench behind it should be backfilled with free-draining granular material (e.g., clear crushed rock or gravel). This backfill provides critical stability and ensures that hydrostatic pressure does not build up behind the wall. The granular fill should be placed in layers, typically 6-8 inches thick, and thoroughly compacted using a plate compactor or hand tamper before the next layer is added. Proper compaction minimizes future settlement and ensures the wall maintains its structural integrity. Care must be taken not to displace the newly laid blocks during the backfilling and compaction process. For tall walls, a drainage pipe might be installed at the base of the backfill, leading to an outlet, to further manage water drainage.

Goal: After the first course of locking blocks is successfully laid and leveled, backfill the area immediately behind it with a layer of clean, free-draining granular fill, such as crushed gravel. This material should be compacted in lifts to provide stable support and proper drainage for the wall.

Tools and materials

  • Mini Excavator (Bobcat 325)
  • Plate Compactor
  • Rakes
  • Shovels
  • Clean Crushed Gravel Generic

What they say

Hide

and all that gets done without me even being there oh yeah so then some of you are probably wondering what the heck is your job stand well my job is to find amazing people that don't want to be babysat line up the projects for them to work on and then just keep them happy and then i get to go do what i want to do and that makes me happy