Final Backfilling and Grading

12:50
15:05
9.5K views

At 12:50 in

Caught in a Jam! Job site crisis

What happens here

Once the French drain pipe is surrounded by gravel, the remainder of the trench is backfilled with excavated soil. The soil is then carefully graded to create a slope that directs surface water away from the house foundation and driveway, preventing pooling and further erosion. This step ensures that both subsurface and surface water are effectively managed by the new drainage system.

Goal: Complete the backfilling of the entire trench with soil and grade the area to ensure proper surface water drainage.

Tools and materials

  • Mini-Excavator
  • Rakes
  • Shovels
  • Soil