Finalize Drainage Trench Excavation

1:53
14:27
68K views

At 1:53 in

TOUGH retaining wall build. Day1

What happens here

After identifying and removing the unsuitable drainage material, the team continues to excavate the area behind the retaining wall. This involves using both the mini-excavator and manual shoveling to create a clean, properly sloped trench that will accommodate the new, correct drainage aggregate and geotextile fabric. The goal is to establish a clear path for water to drain away from the wall's face, preventing future hydrostatic pressure issues.

Goal: The crew finalizes the excavation of the trench behind the wall, ensuring proper slope and depth to prepare for the installation of new, effective drainage components.

Tools and materials

  • Hearing Protection Various — Protecting ears from loud machinery noise
  • Mini-Excavator — Deepening and shaping the drainage trench
  • Safety Gloves Various — Hand protection
  • Shovels Various — Fine-tuning the trench shape and removing stubborn debris
  • Skid Steer — Moving excavated soil and rocks
  • Existing Soil and Rocks N/A — Material removed from the trench

What they say

Hide

first challenge the boys run into is buried utility lines right where we've got to come in and go on be careful yep that's going to want to dig dig in holy crap that is a big wall they've also got a sprinkler system to work around and they're running those three flags over there just gonna make sure that we don't get these but the poster coming out except through the corner yeah okay so what we'll do today is probably get the couple courses off a couple off and then start scraping the rock in the bucket yeah get up there with the mini x and the key cat as the wall is shifted and moving out the pool the plumbing everything is being affected but we can't just go and rebuild the retaining wall as is we're actually going to use a hybrid technique where we borrow the strength from the old wall and add it into the new wall and over the course of the next three videos we're gonna show you exactly how we do that so let's get right into today yeah you can see this whole wall is it's blowing out and tipping and to bridge over those utility lines the boys lay out a system called slat traps and what this does is helps the machinery bridge over it without digging into the yard i like this alternative better than plywood because it folds up neatly and can be reused over and over again to make this hybrid retaining wall system work we only remove the top plane uses the bucket of the mini x to pop out the post to the fence which usually goes pretty good all right guys so we got rained out yesterday we got three about a little under an inch real quick but we're back out on our site today the plan is we're just gonna keep getting the old block out and then get rid of all that gravels to get the most capacity out of the trailer blaine calculates exactly how many blocks this can safely haul so every bucket full they start counting how many blocks go in the bucket and then they'll know how many blocks are going in the trailer all right so that's 42 on there after this so two more then 42 yeah they're gonna try to get 21 block in this bucket and each one weighs 83 pounds all right do me a salad and don't sling a rock said do me a salad and don't sling a but i only counted 20 on this one what did you guys come up with so i found out behind this wall they didn't use clear they got class five which is definitely not helping the water getting through that definitely a contributing factor to the water problems that this guy's having behind this wall so here's where it gets…

Auto-generated from the video audio.