What happens here

Once the old materials are removed, prepare the trench for the new retaining wall's base. The base must be laid on solid, compacted soil, free from old timbers, piping, or tree roots. If over-excavation occurs, backfill with a suitable base material like crushed rock (Class 5 aggregate is a good option if readily available) and compact it thoroughly. Use a plate compactor to achieve optimal compaction, making sure the base material is evenly spread and firmly pressed into place. This process ensures a robust and stable foundation for the entire retaining wall. Deepening and widening the base is acceptable, provided it is properly compacted layer by layer. If poor soils are present, geo-grid can be layered into the base material for additional reinforcement (though not required in this specific case).

Goal: Create a stable, level, and well-compacted base for the retaining wall using crushed rock or Class 5 aggregate, ensuring it's laid on virgin or properly compacted soil.

Tools and materials

  • Plate Compactor (Wacker Neuson VP1550AW)
  • Rake
  • Shovel
  • Skid Steer Loader (Kubota SVL65)
  • Crushed Rock / Class 5 Aggregate

What they say

Hide

have some class 5 that they were hoping to eliminate from their site and it was a perfect material to use as base material to bridge that area back up but you can see we also compacted the heck out of it before we went any further now this is an extra deep and wide base and there's nothing wrong with going deeper and wider on your base as long as you're properly compacting it and bringing it back the right way in fact the more base material have probably the better your wall will perform but that doesn't mean your wall will perform better just by having it you've got to do the right things with it now in this case if we happen to have really bad soils below this retaining wall and we could not perform a soil correction there's a neat trick we could do and that's to deepen the base to create a pyramid and to layer geo grid into the base materials and that is a topic for i think another video entirely all together it's an extremely advanced topic and it's not something that can be applied to every site but once you know how to use it you can start to spot areas and indicators where it's a perfect way to fix a problem area now in this case we just had extra timbers buried and we needed to bring it