Final Backfill and Smooth Grading

12:55
14:50
69K views

At 12:55 in

Retaining walls- SPOTTING short cuts & BAD work

What happens here

Once the retaining wall is built to its final height and all drainage is connected, backfill the remaining area behind the wall with native soils. Use heavy machinery like a skid steer loader to efficiently move and spread the soil. Avoid filling with drainage aggregate all the way to the top unless specifically required for certain landscaping designs; native soils integrate better with the surrounding landscape. Smooth grade the entire area, including any backfill piles and the work zone, to ensure water properly drains away from the wall and structures, preventing erosion or pooling. If rain is expected, cover critical areas like newly excavated trenches with tarps, weighed down by blocks, to protect them from erosion and washout.

Goal: Complete the backfilling process with native soil behind the wall, and smooth grade the entire area to prepare for final landscaping, ensuring proper water runoff.

Tools and materials

  • Rake
  • Shovel
  • Skid Steer Loader (Kubota SVL65)
  • Blocks/Bricks
  • Native Soil
  • Tarps

What they say

Hide

as we get closer to the top we do not continue to backfill all the way up to the back of the top block with drainage aggregate in fact we switch over to using native soils that way the retaining wall flows more seamlessly into the rest of the landscaping if they want to have grass all the way up to the top of the wall they can or whatever else they choose all right guys we are all done for the day getting off a little early because we use up all of the blocks getting some more delivered on monday we got a whole lot done though this is top of wall right here minus the cap so it'll be up a little more and this course is gonna run pretty much to the corner and we're gonna step it down real fast over there all right rain's starting to pick up [Applause] now when we leave a site for rain we'll do a number of different things but one of the most important things you'll see that we have everything smooth graded as much as possible i can't say everything but we'll go through and our backfill piles will get smooth graded our work zone will get smooth graded we don't leave anything rough because that smooth grade really helps dry up the site faster and of course the critical areas that we can't smooth grade like the trenches well we cover up it's turpenner up right when the rain starts can't beat that time