Step 1 · Excavate for Step Base

Mark the outline of the first step's footprint. Dig down to the required depth, accounting for the thickness of the paver base material (e.g., compacted gravel) and the pavers themselves. The excavated area should be wider than the planned steps to allow for retaining the sides. Ensure the bottom of the excavation is level.

Stesso home
SearchSearchBrowseBrowseFeedFeedMy ProjectsMy Projects
Log inLog inSign upSign up

Step 1 · Excavate for Step Base

Mark the outline of the first step's footprint. Dig down to the required depth, accounting for the thickness of the paver base material (e.g., compacted gravel) and the pavers themselves. The excavated area should be wider than the planned steps to allow for retaining the sides. Ensure the bottom of the excavation is level.

Videos for this step

Excavate Base MaterialMark Outlines and ExcavateExcavating for the First Step

Tools and Materials

← Project

How to Build Paver Steps into a Hill

Step 1 of 11·20.5 hr left

1
Excavate for Step Base
120 minutes5 items
2
Install Retaining Edge (Optional but Recommended)
90 minutes4 items
3
Add and Compact Paver Base
180 minutes4 items
4
Lay Sand Setting Bed
60 minutes3 items
5
Set First Row of Pavers
90 minutes5 items
6
Lay Subsequent Rows of Pavers
240 minutes4 items
7
Cut Pavers for Edges and Risers
120 minutes6 items
8
Install Risers and Treads
180 minutes5 items
9
Sweep Joint Sand
60 minutes3 items
10
Compact Paver Surface
60 minutes2 items
11
Final Joint Sand Application and Cleaning
30 minutes3 items