Adjust Wall Placement for Septic Line and Freeze-Thaw
At 6:38 in
Retaining wall BASE failure
What happens here
During excavation, an unforeseen septic line is discovered directly in the planned path of the retaining wall. To prevent potential damage to the pipe and ensure the long-term stability of the wall in an area subject to Minnesota's freeze-thaw cycles (which cause significant ground movement), the decision is made to shift the wall's placement. This 'Plan D' involves moving the wall slightly 'north' (away from the septic line and towards an area with less water saturation), reducing the risk of a rigid wall stressing a rigid pipe due to ground fluctuations. The bridging soil correction techniques are adapted to the new wall alignment.
Goal: Discover and reroute the retaining wall's alignment to avoid interference with an existing septic line and to minimize the impact of freeze-thaw cycles.
Tools and materials
- Measuring Tape
- Spray Paint/Marking Tools
What they say
(1,448 characters)Hide
What they say
(1,448 characters)Auto-generated from the video audio.