Sand is carefully distributed over the finely leveled aggregate sub-base. An ASV Posi-Track VT-70 High Output compact track loader is used to deliver the sand, which is then spread evenly by workers using rakes and shovels. A long, straight screed board is pulled along the 3/4-inch round pipes, which act as depth guides, to create a uniformly level sand bed. This precise thickness of the sand layer is critical; if the sand layer is too thick, the pavers can shift or deflect under pressure, compromising the patio's stability. Once a section is screeded, the guide pipes are carefully removed, and the resulting grooves are filled with additional sand and troweled smooth to maintain a seamless, consistent surface.
Goal: A layer of sand is evenly spread over the prepared aggregate sub-base and precisely screeded using the pipe guides to create a perfectly flat and uniform bed for the pavers.
Tools and materials
- 3/4-inch Round Pipes
- Rakes
- Screed Board (straight edge)
- Shovels
- Trowel
- Sand (for setting bed)
What they say
(1,233 characters)Hide
What they say
(1,233 characters)Auto-generated from the video audio.