What happens here

Before the visible work begins, the initial phase involves removing any existing patio structures to expose the raw dirt. This raw dirt is then thoroughly compacted to create a stable foundation. Following this, a 6-inch layer of recycled Class 5 aggregate is spread over the compacted dirt. This aggregate, consisting of 3/4 inch crushed concrete and asphalt down to fine particles, is then compacted to form a hard, solid sub-base. The narrator emphasizes the importance of compacting the raw dirt and the 6-inch layer of recycled Class 5 to create a nearly solid piece of concrete, ensuring a robust foundation for the patio.

Goal: This initial, off-screen step involves removing existing structures, compacting raw dirt, and laying and compacting a 6-inch layer of recycled Class 5 aggregate to create a solid sub-base.

Tools and materials

  • Heavy Compaction Equipment
  • Recycled Class 5 Aggregate

What they say

Hide

let me explain the first thing that we did that you missed was we removed moved an existing patio then we had raw dirt underneath that patio and we compacted that raw dirt then we put down 6 in of recycle class 5 what this recycle class 5 is it's 3/4 in rock down to minus and it's recycled material so it's a combination of concrete and asphalt that's been crushed and ground up and when you Rec compact that down it turns almost like another like a a whole solid piece of concrete uh and we put six inches of that down the part where you will see us working now is coming up where we prep the final subbase and what we do there is very critical let's get into it here's what we're working