Break Apart Concrete Slabs
At 0:00 in
Demolition Project with Before, During and After Timelapse
What happens here
The process begins with an ASV RT-75 compact track loader, fitted with a hydraulic grapple attachment, aggressively breaking apart sections of the existing concrete pool deck. The operator systematically approaches the edge of the slab, utilizing the grapple's powerful jaws to crack and lift large, unwieldy chunks of concrete. These initial pieces are then moved to a temporary staging area within the work zone, effectively separating them from the surrounding dirt and making them accessible for later loading.
Goal: Use a compact track loader with a grapple attachment to efficiently break and lift large sections of the concrete pool deck, moving them to a designated staging area.
Tools and materials
- ASV RT-75 Compact Track Loader
- Hydraulic Grapple Attachment