Workers begin by manually digging a trench along the sidewalk using shovels. The trench is dug to the required depth to accommodate the retaining wall blocks and a gravel base. Once the trench is excavated, a layer of gravel is laid at the bottom, which will serve as the foundation for the retaining wall.

Goal: This step involves manually excavating a trench and laying down a gravel base for the new retaining wall.

Tools and materials

  • Shovel
  • Wheelbarrow
  • Gravel

What they say

Hide

to see two guys absolutely Step Up and take over every job site has a problem doesn't make a difference what it is the job sites that go well are the ones that you write down on the calendar and you're like can't believe it the job sites that don't go the right way are the ones you just are their status quo we're contractors our job is to handle the problems that we face and the boys today face problems and they absolutely overcome them yeah I'm just going to let the video speak for itself let's just watch the boys work I just want to say I'm really proud of what they accomplish today all right we're done for the day on day one and we got a lot done on day one we got it we got a lot done we didn't really we didn't even get out here until what we really didn't get rolling until 10:30 almost it was almost 11 almost 11 and we're ready for building basically wall tomorrow all will be going in tomorrow

Auto-generated from the video audio.