Backfilling and Continued Wall Construction
8:57
12:16
8.4K views
At 8:57 in
Can they BUILD the wall in time!
What happens here
With the base and returns largely complete, the team focuses on backfilling behind the wall. Zakk, having picked up more rock, begins this process. The main worker continues to build up the wall, using the additional rock for backfill. The goal for the day is to complete the majority of the wall, with final touches scheduled for the following day. The backfilling is a continuous process as the wall is built up, ensuring stability and proper drainage.
Goal: Build up the retaining wall by adding blocks and continuously backfilling to stabilize the structure.
Tools and materials
- Retaining Wall Blocks
- Rock
- Shovels
- Wheelbarrow
What they say
(823 characters)Hide
What they say
(823 characters)Auto-generated from the video audio.