At 9:19 in
Building a new retaining wall and sodding.
What happens here
After the wall is complete, perform final grading of the soil adjacent to the wall, smoothing out any uneven areas created during excavation and backfilling. Prepare the soil bed for sod. Measure the area (length x width) and divide by 9 to get the square yards needed for sod (as sod is typically sold by the square yard). Lay the sod rolls tightly together, ensuring no gaps. Water the newly laid sod thoroughly to encourage root growth and establishment.
Goal: Grade the surrounding soil and install sod to restore the landscape around the newly built retaining wall.
Tools and materials
- Rake
- Utility Knife/Blade
- Sod Rolls Unspecified
- Water Unspecified
What they say
(923 characters)Hide
What they say
(923 characters)Auto-generated from the video audio.