Build Subsequent Courses and Backfill
At 7:45 in
An average Day During the Spring Rush landscaping
What happens here
Continue building the retaining wall by stacking additional courses of units. For interlocking blocks, ensure each subsequent course is offset from the one below (half-bond pattern) to provide strength and prevent vertical joints from aligning. For timber walls, use rebar or large spikes to secure layers together. After laying each course, backfill the area behind it with crushed gravel and compact it thoroughly with a hand tamper or plate compactor. Place layers of landscape fabric between the soil and the gravel backfill to prevent soil migration into the drainage layer. The contractor mentions timber retaining walls and boulder walls that are in disrepair, underscoring the importance of proper construction for longevity.
Goal: Construct the main body of the retaining wall with proper layering and support.
Tools and materials
- Gloves — Protecting hands during construction
- Hand Tamper — Compacting gravel backfill, especially in tight spaces
- Level — Checking levelness of each course
- Plate Compactor — Compacting larger areas of gravel backfill
- Retaining Wall Units — Continuing the wall structure. (e.g., concrete blocks, timbers, boulders)
- Rubber Mallet — Adjusting block/timber placement
- Shovel — Adding gravel backfill
- Crushed Gravel — Filling behind each course for drainage and stability
- Landscape Fabric — Separating soil from gravel backfill
- Pins/Caps — Interlocking retaining wall blocks
- Rebar — Securing timber layers together