Project Halted for Weather, Prep Complete
12:29
13:31
38.2K views
At 12:29 in
TOUGH Wall Job & unexpected delays
What happens here
After a productive day of work in 102-degree heat, all major preparatory tasks are complete. The area around the pool has been re-graded and compacted to ensure proper water shedding. All compromised soil and the tree stump have been removed, and suitable old retaining wall blocks have been cleaned and stockpiled as base material for the new wall. All equipment is parked, and exposed areas are tarped in anticipation of heavy rain over the weekend. The crew is ready to begin building the new retaining wall on Friday.
Goal: Complete all groundwork and prepare for the next construction phase.
Tools and materials
- Skid Steer Loader Cat — Final grading and compaction
- Tarp — Covering materials and exposed areas for rain protection