Calculate Total Rock for Retaining Wall
18:50
34:52
15.4K views
At 18:50 in
The Bible of Job bidding
What happens here
Calculating the total amount of rock needed for a retaining wall involves taking the square footage of the wall and multiplying it by 200 (pounds per square foot of rock). Divide this by 2000 pounds (per ton) to get the total tonnage of rock needed for drainage and base. This example covers a 1200 sq.ft. retaining wall, resulting in 120 tons of rock. This amount must be delivered to the site, adding to material and hauling costs.
Goal: Accurately estimate the rock quantities needed for retaining wall construction.
Tools and materials
- Calculator — Performing calculations
- Rock Various — Drainage and base for retaining wall