Calculate Total Rock for Retaining Wall

18:50
34:52
15.4K views

At 18:50 in

The Bible of Job bidding

What happens here

Calculating the total amount of rock needed for a retaining wall involves taking the square footage of the wall and multiplying it by 200 (pounds per square foot of rock). Divide this by 2000 pounds (per ton) to get the total tonnage of rock needed for drainage and base. This example covers a 1200 sq.ft. retaining wall, resulting in 120 tons of rock. This amount must be delivered to the site, adding to material and hauling costs.

Goal: Accurately estimate the rock quantities needed for retaining wall construction.

Tools and materials

  • Calculator — Performing calculations
  • Rock Various — Drainage and base for retaining wall

What they say

Hide

thing now with a project like this there's a lot that goes into bidding the retaining wall itself there is the price of the block there is the price of the Rock and this is something that I've always calculated separately on a big commercial site I calculate the price of the block delivered with tax take that into consideration the price of the Rock and then there's the price of the geogrid that's part of the material cost but then there's the price of the pins price of the Caps price of the glute these are

Auto-generated from the video audio.