Bidding Retaining Walls: Engineering, Geogrid & Surcharges

11:34
34:52
15.4K views

At 11:34 in

The Bible of Job bidding

What happens here

When bidding on retaining walls, several factors beyond basic dimensions must be considered. First, check if the wall height exceeds local regulations (e.g., 4 feet), which may require an engineer. Site plans, if available, provide proposed and existing grades for accurate material takeoffs. If not, manual measurements are necessary. Crucially, a retaining wall often requires geogrid behind it, which necessitates excavating a much larger area (e.g., 12-14 feet behind the wall) to accommodate the geogrid layers and create safe working slopes, generating significant excess material that needs to be hauled away or temporarily stored. This 'surcharge' (additional pressure from weight behind the wall, like a building or road) further impacts geogrid length and excavation needs.

Goal: Accurately bid retaining wall projects by accounting for engineering, geogrid requirements, and potential surcharges.

Tools and materials

  • Adhesive/Glue — Securing capstones to the retaining wall
  • Caps — Finishing the top of the retaining wall
  • Geogrid Various — Reinforcing the soil behind the retaining wall
  • Measuring Wheel/Tape — Manual measurement of wall dimensions and excavation areas
  • Pins — Securing geogrid layers
  • Retaining Wall Blocks Versa-Lok — Constructing the visible face of the wall
  • Rock Various — Drainage and base material behind the wall
  • Site Plans/Blueprints N/A — Obtaining proposed grades and dimensions for engineered walls

What they say

Hide

close all right Tim now as we look at this retaining wall Tim was actually here when I was building building it now Tim was running a different site for the most of the time but as we were building this retaining wall I actually had a crane so when I was doing the original numbers on this job you see that power pole right there I had an actual crane come out and hold that power pole in place hover it above ground because as we were digging we had to dig back for geogrid to install this retaining well we had to actually dig back right up to the alleyway we actually had to get a permit to use the the easement of the alleyway and we had to hold that that thing up with the crane now as you look at this retaining wall to what are the factors you take into consideration when you bid something like this when you bidden you got to first get your figure out okay is it over 4T yes well that's going to require engineering so now everything we've talked about with the soils and stuff here you're going to want to there's going to be a site plan most of the time for for for a project like this this is already and it's going to have your proposed grades um next to your existing sometimes they're overlaid on the plan so then you can take do a takeoff of that too and figure out how much soil is coming out based off of the plan so it gets you even closer so now if this is residential you don't always have a survey you don't always have a situation so now you got to take do your measurements and and figure out you know the the the divided by 27 get your get your numbers that way so so and in a retaining wall like this though we've got to calculate the actual square footage cuz they don't give us the square footage on the plan this had a blueprint and it had just bottom of wall elevations and top of wall elevations and we have to actually go through and hope and pray that the surveyor got all of their elevations you want to double checks you get your wheel out and you get your height of the you know you know the height of the wall some cuz with when you're coming here to measure this initially you you have a hill here so how you going to tell where that wall you know height of the wall is that's when you go off from the blueprints if they're calling out a bottom of wall at 890 and the top of wall at a 9005 that's telling me that I got a 15t tall wall right there in that corner and if the wall is 50 ft long at 15t tall I'm going to calculate that as part of that square footage…