What happens here

The discussion moves to calculating soil volume for excavation. The formula for cubic feet of soil is Length x Width x Depth. For sloped terrain, this result is divided by 2. To convert cubic feet to cubic yards, divide by 27. Finally, to account for 'fluff' (soil expanding once excavated), multiply the cubic yards by 1.25. The total fluffy cubic yards determines the number of truck loads, considering a tri-axle dump truck hauls approximately 15 cubic yards. Coordinating truck cycles to match operator productivity is crucial to avoid idle time and wasted overhead.

Goal: Determine precise soil volumes and optimize hauling logistics for excavation.

Tools and materials

  • Calculator — Performing volume and conversion calculations
  • Measuring Tape — Measuring length, width, and depth of excavation areas
  • Tri-Axle Dump Truck Various — Hauling excavated soil. (Capacity: approx. 15 cubic yards)
  • Excavated Soil N/A — Material to be removed from the site

What they say

Hide

and actually put it in there and then one of the things too that needs to be taken into consideration is you must calculate your overhead cuz if you said you're going to calculate how long it's going to take you to to tear that building down it's not just tear the building down it's to load those trucks how long of a round trip are those trucks making because if you're sitting and waiting for trucks then you've got an operator chewing up overhead that isn't being productive so you've got to be able to coordinate I need to have enough trucks on site so that the operator doesn't get overwhelmed but you also don't want him sitting there twiddling his thumbs in between loads not doing anything you want him to be able to continually operate at a smooth pace so you've got to actually time it where I've gone to the site I've gone on a job site like this and I physically drone drove the site from here to the dump back here to the dump and back so I knew exactly how long a round trip was going to take because when you have enough trips it adds up fast so when we were originally looking at it the soil for this came down to right about here so this from this point here up to there was just a hill so what would you do if you're looking at this going I got to cut all this out I got to get rid of all of this what would you do so what I would do is I'd find the depth how far back I'm going how long of a run I'm doing and how wide it is so or how high it is so I'm getting those two three things in there I'm adding those up and I'm dividing it by two because it's a hill it's a slope so it's almost like a triangle and then I would do that by how many cubic yards I had and then I would multiply it by 1.25 for the fluff because it's going to take up a little bit more room in the truck once you unpack everything and pull it all out and then I would figure out how many truckloads it would take like you said how long it takes to go to this to The Dumping back here I know it probably takes 25 minutes one way to the dump I figure in hey it's going to take him sometimes 15 20 minutes to dump you don't always dump right away so I add a little bit bit of fluff in the running time as well too so we never lose out on that so the actual calculation is length time width time depth divide by 27 * 1.25 automatically converts space to cubic yards to fluffy cubic yards so length time width time depth creates the cubic yard Vol or it creates the volume and that's in cubic feet you divide by…