Excavate Subgrade and Remove Organic Material
1:11
20:40
677.1K views
At 1:11 in
Pavers-Mastering the basics
What happens here
Operate a mini-excavator to dig out the path area. It's crucial not to 'over-dig' the area, meaning digging deeper than necessary, as refilling with loose soil can compromise compaction. If over-digging occurs, any loose dirt must be thoroughly compacted. Importantly, all organic material (topsoil, roots, etc.) must be completely removed, as it decomposes and causes significant settlement over time. Continue excavating until stable, inorganic subgrade is reached.
Goal: Excavate the soil to the predetermined depth, carefully ensuring no organic material remains as it can lead to future settlement issues.