What happens here

With all connections made, slowly turn the main water supply on at the water meter. Once pressure is established, slowly open the newly installed shut-off valve at the house. Carefully inspect all new connections for any signs of leaks. The system is now operational, providing temporary water to the house.

Goal: Verify the temporary water line is functional and leak-free

Tools and materials

  • Newly Installed Shut-off Valve Apollo — Controlling water flow to the house
  • Water Meter Neptune — Controlling the main water supply