Prepare and Adjust Class 5 Base
0:33
18:35
1.2M views
At 0:33 in
Installing Brick pavers -start to finish day2
What happens here
The project begins by confirming the required depth for the Class 5 base material. The string line, representing the top level of the finished pavers, is established. The pavers are 2 3/8 inches thick, and a 1-inch layer of sand is planned. This means the Class 5 base needs to be 8 5/8 inches below the string line. If the existing Class 5 is too high, a skid-steer loader is used to scrape down the base material to the target elevation.
Goal: Achieve the precise depth for the Class 5 base material, 8 5/8 inches below the finished paver level.
Tools and materials
- Measuring Tape — Measuring depths from the string line
- Skid-Steer Loader Caterpillar — Moving and scraping down Class 5 base material
- Class 5 Base Material — The compacted foundational layer for the pavers
- String Line — Establishing the final elevation for the pavers
What they say
(1,119 characters)Hide