Creating Initial Control Joints
At 0:58 in
How the Pro's Pour Concrete with Victory Outdoor Services #3
What happens here
To prevent random cracking as the concrete dries and shrinks, control joints are cut into the surface. First, a chalk or string line is snapped onto the concrete to provide a straight guide. Then, a 'walking jointer' (a jointer tool with long extension handles) is carefully pushed along this snapped line. The goal is to make a clean, initial groove that will guide any future cracking along this specific line. The operator must maintain a steady hand and eye to keep the jointer precisely on the marked line.
Goal: This step demonstrates the use of a walking jointer to create the initial control joints in the concrete, which are essential for managing cracking.
Tools and materials
- Extension Handles
- Nylon String Line (Chalk Line)
- Walking Jointer