What happens here
After securing the joists, precisely measure and mark the joist lengths. For an 8-foot wide shed, the joist length should account for the rim joists (3 inches total) and the thickness of the sheathing (1 inch total), resulting in a 92-inch joist length. Use a tape measure to define this length on the joists. Then, pull a chalk line across the marked ends of all joists to create a straight cutting guide. Using a circular saw, carefully cut off the excess material to ensure all joists are uniform in length, providing a clean and square edge for the sheathing.
Goal: Ensure joists are uniformly sized and square for sheathing installation
Tools and materials
- Chalk Line — Creating a straight cutting guide
- Circular Saw Makita — Cutting excess joist material
- Tape Measure — Marking joist lengths