The crew begins the retaining wall installation by using a mini excavator to dig out the necessary trench for the wall's foundation. Existing old retaining wall blocks are removed during this process. The backfill soil, which is suitable for reuse, is separated from the debris that needs to be discarded. A plate compactor is then used to compact the initial soil bed, ensuring a stable and level base for the first course of blocks.

Goal: This step involves excavating the trench, removing old blocks, separating reusable soil, and compacting the base layer for the new retaining wall.

Tools and materials

  • Mini Excavator — Digging the trench and moving large quantities of soil
  • Plate Compactor — Compacting the soil base for stability
  • Shovels Various — Manual digging and shaping of the trench
  • Skid Steer — Moving excavated soil and gravel for backfilling

What they say

Hide

We have very little left. Mostly it's top covers, planning, and cleaning. So we hope to finish, if not all of it today, then at least most of it , because tomorrow, Friday, is the opening of the fishing season. And as far as me, Blaine, and Alex are concerned, it should be a public holiday. Yes, that's right. So the guys plan to work hard today. While the guys are clearing out the trailer, Blaine is preparing the next phase of excavation. He is trying to separate the soil for backfilling from the retaining wall blocks that are going to be thrown away. If the soil is suitable for backfilling, he throws it into the bucket of the skid steer loader so we can reuse it. He uses the offset boom of a mini