What happens here
Using an excavator, dig two distinct trenches along the marked path. The first is a wider, flat zone designed to accommodate the geogrid reinforcement, which will extend horizontally behind the wall to provide stability. The second is a narrower, precise trench that will serve as the footing for the actual retaining wall blocks. Extreme care is vital when digging the smaller trench to avoid going too deep, as over-excavation would require backfilling and recompaction, compromising the foundation's stability. All organic material should be removed from the excavation area to ensure a solid base.
Goal: Carefully excavate two trenches: a larger, flat zone for the geogrid reinforcement and a smaller, precise trench for the retaining wall blocks.
Tools and materials
- Excavator (Bobcat 325)
- Shovel