Compacting Base and Laying First Course
7:00
25:06
3.1M views
At 7:00 in
Crazy Neighbor Calls the Building Inspector on us
What happens here
The base layer of crushed rock is compacted using the 150lb plate compactor to create a solid, stable foundation. After compaction, the initial course of interlocking blocks is laid directly onto the leveled rock base. Pins are then hammered into the designated channels of these blocks, ensuring they sit firmly in the slots of the blocks below, providing an automatic setback for each course.
Goal: The crushed rock base is compacted, and the first course of interlocking blocks is carefully laid and pinned to ensure a strong and level foundation.
Tools and materials
- 150lb Plate Compactor
- Level
- Rubber Mallet/Sledgehammer
- Interlocking Retaining Wall Blocks
- Retaining Wall Pins
What they say
(1,134 characters)Hide
What they say
(1,134 characters)Auto-generated from the video audio.