Loading and Hauling Excavated Materials
5:57
29:38
109K views
At 5:57 in
Building a Retaining wall start to finish #1
What happens here
Utilize the skid-steer loader to scoop up the separated materials and carefully load them into the dump truck. The newly constructed ramp provides the necessary height for the skid-steer's bucket to clear the high sides of the quad-axle dump truck. The operator must execute precise maneuvers to avoid damaging the truck, especially its side walls. The material is typically loaded heavily towards the rear of the truck for stability.
Goal: Remove all unwanted excavated soil and debris from the job site.
Tools and materials
- ASV RT-75 Posi-Track ASV — Loading materials into the dump truck
- Bucket attachment ASV — Scooping and depositing materials
- Excavated Soil/Debris N/A — Removal from the site