Prepare Base for Steps and Wall
0:50
24:16
125.6K views
At 0:50 in
Building a retaining wall #2 - "How we Base walls"
What happens here
The first phase of construction involves preparing the foundation for the integrated steps and the main retaining wall. Precast concrete steps are used, noted for their flat top and bottom surfaces which simplify leveling compared to natural stone. The base is constructed using 3/4 inch clear gravel, which provides a solid, well-drained platform for the blocks and steps. Workers are shown carefully leveling each section of the base to ensure stability.
Goal: Establish a stable and level base for the retaining wall and steps.
Tools and materials
- 3/4 Inch Clear Gravel
- Dead Blow Hammer
- Level
- Plate Compactor
- Shovel
What they say