Cutting and Laying First Course of Blocks
At 6:48 in
Turning a Hill into a Flat(er) backyard pt/2
What happens here
Blaine uses a Husqvarna gas-powered cut-off saw to precisely cut retaining wall blocks to fit against the house's foundation. The saw, surprisingly, starts easily despite not being used for ten months. After the initial blocks are cut and placed, Sam begins laying the first course of blocks along the string line. Both workers then 'toe in' the blocks, meaning they backfill with excavated soil both in front of and behind the blocks immediately after placement to secure them. This step continues for multiple courses of the buried section of the wall, with careful placement and leveling of each block.
Goal: Install the initial courses of retaining wall blocks and secure them with excavated soil.
Tools and materials
- Dust Mask — Respiratory protection from concrete dust
- Ear Protection — Hearing protection from saw noise
- Gloves — Hand protection
- Handheld Level Stanley — Checking the level of each block during placement
- Rubber Mallet — Adjusting the position and level of the blocks
- Safety Goggles — Eye protection from cutting debris
- Shovels — Moving excavated soil for 'toeing in' blocks
- Excavated Soil N/A — Backfilling and 'toeing in' the blocks
- Retaining Wall Blocks — Constructing the retaining wall courses