Gravel Base and First Block Course
0:09
15:38
13.4K views
At 0:09 in
Thats a problem
What happens here
After the trench is dug, gravel is brought in by the skid steer and distributed along the bottom of the trench. A plate compactor is then used to firmly compact this gravel layer, creating a solid and level foundation. The first layer of retaining wall blocks is then meticulously laid on top of the compacted gravel, with workers using levels and measuring tapes to ensure proper alignment and height. This establishes the initial footprint of the wall.
Goal: Following excavation, a gravel base is laid into the trench and compacted. The first course of retaining wall blocks is then carefully placed on this level, compacted base, ensuring a stable and even foundation for the wall.
Tools and materials
- Levels (Spirit/Laser)
- Measuring Tape
- Plate Compactor
- Retaining Wall Blocks
- Skid Steer (Compact Track Loader)
- Gravel