Spread the Crushed Stone Base
At 14:19 in
Regrading the muddy parking lot pt 2
What happens here
Position the dump truck over the prepared subgrade where the base layer is to be installed. Carefully raise the truck's bed to begin tipping the crushed stone out. As the material flows out, slowly drive the truck forward to create an initial, even layer of crushed stone across the driveway area. The goal is to distribute the material as uniformly as possible to minimize the need for extensive additional spreading by other equipment. This forms the initial base, which will be further graded and compacted in subsequent steps (not fully detailed in this video).
Goal: Carefully dump and spread the crushed stone evenly over the prepared subgrade to create the foundational layer of the gravel driveway.
Tools and materials
- Dump Truck
- Class 5 Crushed Stone
What they say
(112 characters)Hide
What they say
(112 characters)Auto-generated from the video audio.