Unloading Interior Demolition Materials
7:02
34:29
58.1K views
At 7:02 in
Loading & Hauling in freezing weather
What happens here
Transport the skid steer loaded with interior demolition materials to the main debris pile. Raise the bucket and carefully dump the contents, aiming to consolidate the pile as much as possible. Keeping the pile 'concise' is essential for efficient tarping and to optimize space for future 40-yard dumpsters that will be brought in to haul away the material.
Goal: Drive the skid steer to the designated staging area and dump the interior demolition debris onto a growing pile. The goal is to keep the pile as concise as possible to prepare it for tarping and eventual collection by 40-yard dumpsters.
Tools and materials
- Skid Steer Bucket
- Skid Steer Loader