What happens here
The builder demonstrates the nailing schedule for headers, typically requiring fasteners every 12-16 inches on-center. He shows two methods for this: stacking nails directly on top of each other or offsetting them. He then explains how to precisely calculate the length of jack studs needed for door and window openings. For a rough opening height of 82 1/2 inches to the bottom of the header, he subtracts the 1 1/2 inches thickness of the bottom plate to determine the correct jack stud length. Finally, he uses a circular saw to cut the jack studs to the calculated length.
Goal: Correctly nail headers and calculate/cut jack studs for openings
Tools and materials
- Circular Saw Makita — Cutting lumber to specified dimensions
- Header Lumber — Demonstrating proper nailing patterns for structural stability
- Jack Studs — Providing vertical support for headers in door and window openings
- Measuring Tape — Measuring for accurate jack stud length calculations
- Pencil Dixon — Marking precise cuts on lumber
- Pneumatic Nail Gun Paslode — Nailing header components
- Speed Square — Ensuring square marks for accurate cuts