What happens here

Eight yards of river rocks are delivered to the site by a dump truck and unloaded in the driveway. These rocks will be used for the dry creek bed. The Cat skid loader is used to transport the rocks from the driveway to the work area. To facilitate access for the skid loader, large wooden 'slat tracks' are laid out as a temporary path over a paved patio area, preventing damage to the existing hardscape.

Goal: Deliver river rocks and create a protected access path for the skid loader.

Tools and materials

  • Cat Skid Loader Caterpillar — Transporting rocks from the driveway to the work area
  • Dump Truck — Delivering large quantities of river rocks
  • Slat Tracks — Creating a temporary access ramp over a paved patio
  • River Rocks — Constructing the dry creek bed

What they say

Hide

stone. There are eight cubes of stone there. But they need to be installed in place, which means they will have to start building a ramp through the retaining wall. I think we can do it. Will it be difficult to get there, here? Yes, I think everything will be fine. I think you should build a ramp here. Yes. So that you can climb up here. Straight up, and then you won't have to turn around. Yes, it's always...it's always risky. They have too much land where the dry riverbed will be , but that doesn't mean it will go to waste. She will go to build a road to access the other side of the house. But the area is too narrow for the CAT to even turn around. Therefore, the Bobcat mini excavator must remove any boulders or obstacles in the way so that the CAT can access the backyard and begin building the ramp. They need decking because the back of the yard can only be accessed through the patio pavers. Then they will have to build a ramp up through the lower retaining wall to drive a