Concrete Delivery and Initial Pour
17:20
23:35
19.8K views
At 17:20 in
I DON'T TRUST COLLEGES!
What happens here
A large concrete mixer truck arrives on site, backing up to the prepared formwork. A worker guides the discharge chute of the truck, allowing fresh concrete to flow into the forms. The concrete is initially poured in a section of the slab, with workers using shovels and concrete rakes to roughly spread the material and prevent excessive mounding. The concrete is placed close to its final position, ready for subsequent leveling.
Goal: The concrete truck arrives, and the initial pour of concrete is managed directly from the truck's chute into the prepared forms.
Tools and materials
- Concrete Mixer Truck (Cemstone)
- Concrete Rake
- Shovels
- Wet Concrete
What they say
(302 characters)Hide
What they say
(302 characters)Auto-generated from the video audio.