When measuring the project area, especially for irregular or curved patios, break the area down into easily calculable squares (e.g., a semicircle can be approximated by a series of rectangles). While initial estimations can be slightly approximated to provide a quick quote, for final billing, absolute accuracy is paramount. Contractors often make the mistake of only measuring the installed area, but material costs include all purchased blocks, even those cut and discarded due to design requirements (like curved edges). Therefore, use the supplier's detailed spreadsheet or invoice, which itemizes every block delivered, to calculate the exact quantity of materials purchased, including those used for cuts and waste. This ensures all material costs are accurately passed on to the customer.

Goal: Utilize a method of breaking down irregular shapes into measurable squares for initial estimates, but rely on supplier invoices for final billing to account for all purchased material, including cuts and waste.

Tools and materials

  • Supplier Invoices/Spreadsheets
  • Tape Measure
  • Whiteboard/Sketch Pad

What they say

Hide

the area again. Let me show you why you shouldn't do that. I'll check if I'm writing with a marker. This is important. Therefore. On a semi-elliptical object like ours. This work was essentially a semicircle. Of course? I break all my tasks into squares. I measure in squares because I'm not smart enough to calculate the radius of a semicircle at an angle of 33 degrees on an object. But I'm smart enough to figure out: side times side is going to give you the area in square feet. Of course? So if I measure a 5 by 3 square, I know that it contains 15 square feet. And then I say: you know what? There is something superfluous here. I'll reduce it to nine or seven. At this stage, I'm estimating roughly because I don't need precision for the initial measurement. I need to be approximate. I do n't have to be precise. So I go through and measure the entire project with squares. But in the end, it will ruin you. You don't want to measure with squares at the end. So, to give you a better idea, when I first meet with a client and I need to figure out how many square feet their project is, I break their work down into squares. In this case we have 1, 2, 3, four squares. Each square has, well, let's say, 15, 9, and 9. This one is nine. This one is also nine. So, 35. 39, 48 square feet—that will be the project area. This is just an example. Good. Just an example : at the end of the job, if I leave now, the client pays, let's say, $20 per square foot. They will want to know exactly how many square feet are in this property. They're going to want to know this very precisely because it's costing them $20 per square foot. So you are obligated to get the correct number at the end of the work. I hope I didn't confuse you too much. If so, write to me and I will explain in more detail. At the beginning of the job, I get a rough figure to give them an estimate. At the end of the work, instead of re-measuring , because this is where you can make a mistake. Let's say this is the end of the work, I have the same semicircle, and I'm taking measurements. It so happens that I don't include this area here, and that's right, because there's no patio there. But to make these semicircular cuts, I have to cut all these paving stones. I have to cut all these blocks, I throw them away, and they are no longer on the site. You can't measure them anymore. I still had to buy them as a contractor. I still had to deliver them to the facility. I still had to cut them up and then physically throw…

Auto-generated from the video audio.