Laying the First Course of Blocks (Critical Detail)

9:11
15:59
76.2K views

At 9:11 in

Double Terraced wall Crashes down pt1

What happens here

The first course of blocks is the most critical as it sets the foundation for the entire wall. Begin laying the blocks directly on the prepared and compacted angular stone base, typically starting from a corner or a fixed point. For each block, use a dead blow hammer (or a rubber mallet) to gently tap it into place until it is firmly seated. Immediately check the level of the block, both front-to-back and side-to-side, using a standard level (e.g., Johnson Level & Tool magnetic level or similar). If a block is not level, lift it, adjust the aggregate beneath it (adding or removing material by hand), and then re-seat and re-check the level. Repeat this process until each block in the first course is perfectly level. The video emphasizes that for mortarless systems, the base must be perfect, as there is no mortar to compensate for imperfections. Pay close attention to the setbacks between blocks (e.g., half-inch per course) as specified by the block manufacturer. In a team setting, one person (the 'baser') stays in the trench, focusing solely on leveling, while another 'feeds' them blocks and assists with major base adjustments.

Goal: Meticulously lay the first course of retaining wall blocks, ensuring each block is perfectly level and aligned, which is crucial for the stability and aesthetics of the entire wall.

Tools and materials

  • Dead Blow Hammer (or Rubber Mallet)
  • Level
  • Shovels/Rakes
  • Retaining Wall Blocks

What they say

Hide

on a bigger retaining wall project we'll split into teams of two a basing team and a wall building team the basing team will have one dedicated baiser and then a person feeding the baser the baser never really has to leave the trench they can concentrate on their work and you'll see why that's important in just a minute all right guys I'm going to change things up just a bit here at the end of this video we're gonna do a very detailed breakdown on how to base a difficult section of this retaining wall I saved it for the end because I know it's not for everybody it's definitely slows down the flow of the video but I know a few of you guys love that really nerdy detailed information because I know I do I absolutely love it I included it at the end so catch that after my outro if you're interested in that stuff but let's keep going with this one though as alex is basing out in front of the boys they start toeing in the wall they fill just up to the front face and back of the first course of wall and this helps lock everything together and stabilize it prepping it for the second course to go on with the bottom course coat in as far as they want to go the boys are gonna prep to get the second course on now it's quiz time does anybody know what Alex is doing with this with the base course Thoth in they can lay the second course down which ties everything together so now there's rain in the forecast and the