What happens here
Initially, the video shows a partially excavated trench along the base of the house. The first step involves adding a layer of crushed gravel (aggregate base material) into this trench. A skid steer is used to dump the gravel, and workers manually spread and level it using shovels and rakes. This leveled gravel layer will serve as the stable foundation for the retaining wall blocks.
Goal: Begin by preparing the trench for the retaining wall foundation. This involves digging the trench to the required depth and width, then adding and leveling a gravel base to ensure a stable and well-drained foundation for the first course of blocks.