Avoid material shortages when doing concrete or fill πŸ‘ #concrete #measure #filldirt #learn

0:30
5.8M views

Video by BAS Renovations

BAS Renovations

What happens here

This video explains common reasons why DIYers and contractors frequently find themselves short on bulk materials like concrete for their projects. It visually demonstrates the volume of a cubic yard and a cubic foot, and then illustrates how small inaccuracies, such as setting forms a half-inch too high or over-digging a base by a half-inch, can significantly impact the required material quantity, leading to shortages.

Transcript

Hide

This is why you're always short on material. There's 27 cubic feet in a cubic yard, and it takes 1 cubic yard or 27 cubic feet to fill 81 square foot at 4 in. So, if I dump this box 27 times or the yard box once, fill these forms. But, if you set these forms a half inch higher or over dig your base, and you'll be short 10 square feet or more than 3 cubic feet. Thanks for watching.

Auto-generated from the video audio.